Friday, February 7, 2014

Expansion Update 1: Hello New Kosme Bottling Line!

As some of you may have noticed, we announced (somewhat secretly) that The Bruery is expanding during 2014! Quality is a huge priority for us, and we are thrilled to be introducing some new (and pretty big) measures to make sure we are producing beer that excites us and and is exemplary of the highest quality.

An illustration of our brand new Kosme bottling line, which is on its way to us this year.

There are a couple phases of growth and equipment additions we're working on this year. One of the first items we're adding to our company is a brand new bottling line. Expected to arrive in July this year is a 16-head Kosme line from Krones, arguably the highest quality manufacturer of beer bottling lines in the world. The addition of this line to our production means we can look forward to several improvements once everything is up and running.

Monday, December 23, 2013

Cleaning the Slate -- Beer Issues from 2013

Wow, it’s been a crazy year. Our barrel program has come to life, we’ve released approximately 45 different bottled releases this year, and we are starting to fill the large pair of shoes we have created for ourselves. Part of filling in those shoes is finding our weak spots and fixing them. This year we’ve had five releases that didn’t go as planned -- we want to tell you about them and what we’re doing to avoid this in the future.



Beers That Have Had Issues


As you may recall, earlier in the year we stopped shipments of Ebony & Oak and issued refunds. This beer began souring and building excess carbonation a few weeks after it was released. While bourbon barrels are usually quite stable due to once having bourbon in them, they aren’t immune from causing beer spoilage. However, usually that spoilage happens during the time in the barrel and we catch it before packaging.

Wednesday, September 14, 2011

Propagating Greatness


We got a new delivery in today!

Our yeast propagator came in the mail!

For those who don't know, we primarily use a single strain of yeast for about 85% of our beers.  It's a Belgian-style yeast strain that is highly attenuating (it eats a lot of sugar) leaving our beers with a very desirable, dry finish.  It's attenuation is also important because we make a lot of beers that are over 8% or even over 10% alcohol and it takes a very strong yeast strain to keep on working and break the sugars down until we get to that strength of beer.  

A problem that we often run into because of this yeast and our massive use of it is that we often don't have enough.  Many of our strong beers basically destroy a yeast pitch after it is done fermenting because of how strong the beer is.  Some of our other beers are simply too unique to reuse the yeast from them for another beer.  For some of our smaller beers, however, we can re-pitch the yeast from one fermentor into another, often up to 8 or 9 times.  In fact, yeast can multiply while fermenting, it must get excited while making all that beer, and we can end up with more yeast after a fermentation than we started with.  Because of this quality of yeast, homebrewers and professional brewers alike will make propagation batches.  In a homebrew, this might just be taking the small vile of yeast that you pick up from a homebrew shop, adding it to a small flask of wort (sugar water made from malted barley) and after a few days of fermenting you'll have enough yeast for a batch of high gravity homebrew.  

Here at The Bruery, part of the reason that we often make low alcohol, draft-only beers like our Humulus ales or 714 is because besides the fact that they are exciting to brew, it works as a giant propagation batch that we can harvest yeast from.  We love making these one-off beers and will continue to do so, but the problem with using them as prop batches is that it means we have to fit them into our brewing schedule at specific times and they take up fermenters that we might need more for something else.

So, we finally got ourselves a yeast propagator.  This bad boy, a 120 Liter Newlands, is going to be our savior.  It's only job is breeding yeast.  We add some wort and some of our house yeast and it efficiently feeds and aerates and does everything that yeast needs to grow up big and strong.  It's like hiring a nanny for our yeast babies.  Now we can get back to making beer while Newlands takes care of the yeast until we need it.



carefully and frightfully unloading our new toy.


Only the best gifts need a drill to unwrap.


Everybody is so excited to see it!

Tada!


One last thing... Jay must bless the propagator.


Monday, December 29, 2008

What should I be posting about?

When I was in the initial phases of starting The Bruery, this blog was a great way for me to bitch and complain.  Today, I don't have much to bitch and complain about.  Well... I always have things to complain about, but the blog isn't the greatest medium for my bitching these days.

Many people discovered The Bruery from this blog, and I want to keep it a source of information about beer and share how I started a brewery.  I'd like to gather some comments on this and see what you'd like me or anyone at The Bruery to write about.  Post away and let me know what you'd like to know.

Potential topics I was thinking about because they are relevant to what I'm currently doing (some may be interesting to a general audience, some are extremely dry but useful to aspiring brewery owners):

-- Choosing Distributors
-- Expansion (Space, capacity, and employees)
-- Barrel aging / approach to flavor
-- Merchandise
-- Guide to getting a job in a brewery
-- A Checklist to State and Federal Regulations
-- Taxes
-- A Guide to Successful Delegation (I wish I could find a good source on this right now!)
-- Importance of tasting rooms / tours in production breweries
-- The Bruery in 10 Years: How Big is Too Big?

Wednesday, March 12, 2008

The Progress of the Past Year


Note: I wrote this about a week ago and haven't had time to finish up and post it until now. We have three batches in the fermenters (approximately 1,860 gallons of beer/wort) fermenting away. I'll fill you in on the last week in a day or two when I get a chance to catch my breath.

---

Last year around this time I was dealing with real estate brokers trying to find a place to lease. I didn't know where I was heading at that time-- I just knew I wanted to start a brewery somewhere in Orange County and I'd accept just about any building to brew in (given a few modest requirements). I had no idea how much work starting a brewery would be, and just how great it would turn out. I'm very excited about the future of The Bruery, and I can't wait to share it with you. We're on the brink of brewing Batch No. 1, which is finally happening tomorrow. We brewed our yeast propagation batches last Friday and Saturday, which went surprisingly smooth, and now have healthy yeast to brew a bunch of beers in the next two weeks.


The following are some pictures from the nine months, from empty warehouse to functional brewery:




My brewhouse in January of 2007 when I was deciding on whether to purchase it.

The picture I took of 715 Dunn Way before I leased the space.

Empty warehouse, soon (or not so soon) to be a brewery.  Taken in May of 2007.

Moving the equipment from Windsor to Placentia in June or July of 2007.



Some Pliny the Elder to celebrate moving the equipment inside the warehouse.

Cutting the concrete.

Removing soil / grading.





Vestibule framing.

Flooring installed.

Moving and mounting the glycol chiller to the roof.

Setting the tanks upright.

My beautiful wife Rachel bringing us lunch during our brewing of the propagation batch.

Under the mash tun / grant.







Finally, getting to mash in!

Thursday, January 10, 2008

Power Has Arrived!

Title says it all.  We finally have power from Edison!  Those of you who have been here in the dark know what a great feeling that is for me.  I couldn't wait to roll up the many extension cords we had running all over the place around here.  The unfortunate part is I could finally see how filthy the restrooms are.

12 Days Til the Yeast Arrives...

The completion of the construction schedule now revolves around an order of yeast.  We are expecting our first yeast pitch from White Labs on the 22nd.  Yeast is a delicate organism, and should be used soon after propagation for it to work under the most favorable conditions.  I'd like to pitch it in a propagation batch on the 22nd to get enough yeast for a 30 bbl batch of Batch No. 01 and the following batch.

There's still a lot of work to complete, but it's not impossible that we'd be ready for the propagation batch on the 22nd.  The key areas to finish are in welding, electricity to the brewing equipment, auger installation, utilities (gas/electric) approval, and City / Health Department approval.  

It's not really about the yeast, but more about setting a deadline and doing everything in my power to meet that deadline.  It's about getting this brewery up and running after a long 9 months of trying to get this off the ground.

Despite all of the tasks remaining, The Bruery is finally looking like a brewery.  The brewhouse and all tanks are leveled and anchored, almost all equipment is in our possession, and my enthusiasm about running a brewery is as high as ever.  

It is hard to believe that a year ago I was putting together a business plan and looking around aimlessly for a location that would be perfect for a brewery-- mostly I just wanted floor drains already there.  Finding floor drains already installed was my goal, because I thought that would be the most expensive part of the construction process.  It's funny looking back on how little I knew.  It is humbling and frightening to realize that I'll think a year from now and have the same thought on how little I knew a year ago about running a brewery.  It'll certainly be a learning experience.  

I look forward to sharing my failures and successes with you.

Past Events in Pictures


In December the Hollingshead family invited me to speak at their Winter Tasting.  I introduced about 11 beers, giving any information I know about the brewery, how the beer was made, why Belgian beers are so great, and so on.  Kenny did a great job pimping The Bruery, comparing me to Vinnie Cilurzo (a stretch, I know!), and announcing he'd be the first account to sell my beer.  The last beer of the night was my Quadrupel, which went over well with the crowd.


Our good friend Spence and Rachel at the tasting.

 Tyler moving around a 15 bbl fermenter

The 30 bbl fermenter being moved over the curb

Glycol chiller being placed on the roof platform

Julian helping out in raising the brite beer tank

The lifting of the 30 bbl fermenter.  My contractor Bob did a great job in getting this beast up safety, and without any expensive riggers!

The two tanks in their permanent location.

Monday, December 17, 2007

Brewing Equipment: Getting By

As a continuation of the last thread, Nicholas asked: "Right now I'm looking for info on prices for new/used equipment so I can price out potential setups. I can find books upon books about beer, but nothing on equipment. Also, I'm a little spotty on what equipment/tanks do what and how many are necessary as a bare minimum, but I can't find any such reference."

For finding used equipment, I'd stay away from books as numbers will be outdated. Stainless steel prices change all the time, and used equipment isn't immune from stainless steel commodity prices. Instead, contact Brewing Equipment dealers such as Ian Day at North American Brewing Services, Vince Cottone at Sound Brewing Systems, or Jason Ager at Ager Tank & Equipment. Last year around this time I was looking for a used system and was finding it difficult to make an offer on one as they were usually sold within a few days of being offered for sale. I doubt that's the climate today with malt and hop shortages. Also, check ProBrewer Classified Forums. Sometimes used systems are listed on the Brewers Association Forum, but you'll have to sign up to the Brewers Association as a Brewery in Planning (around $300) to get on the list, plus you get a subscription for New Brewer magazine and get a better rate for the Great American Beer Festival and Craft Brewers Conference. Speaking of the Craft Brewers Conference, it's coming up this April in San Diego, and I'd recommend any prospective brewery startup to attend the seminars and get to know your suppliers.

The cost of brewing systems vary widely based on brew length (how much wort is being made at a time), how many vessels, what's included (pumps, hard piping, heat exchanger, etc.), steam or direct fire, whether the steam boiler (for a steam powered system), fermenters and a glycol chiller are included, and so on. For a 2-3 vessel 15-20 bbl system with everything you need, plus an acceptable amount of fermentation/cellar capacity (let's say 60-90 BBL's worth) will run around $150,000 - $200,000. A new system with everything you need will run around $300,000 from the value conscious suppliers. I'm sure there are better deals to be had, but this is just a general number you could expect.

The lowest amount you could expect with everything you need would be $50,000 for a bare bones 2 vessel system of 5 BBL or less. You can expect to use hose to connect your vessels during brewing, and you probably wouldn't need to spend too much on malt handling (augers, large mill, etc.) for this size of system. I wouldn't recommend a system under 15 BBL as you'll find making a profit in this industry is not easy. Having to brew 5 times a week on a 4 BBL system is a lot less efficient use of your time than brewing once on a 20 BBL system.  If that's all that can be afforded, and it's just a starter system, then it might work for you.  Just don't expect to make any money, and prepare to lose a bunch.

You could spend less on a single vessel malt extract kettle, but I'd stay away if your goal is to make great beer. If you're looking to spend less than $50,000 on equipment, I'd consider mead making as you'll only need a boil kettle and fermentation space.  Plus, mead is increasing in popularity and there are very few commercial mead makers today.

As for what the vessels are used for-- I'd recommend getting into homebrewing and visiting breweries! I'll give a basic overview from what you need from the beginning of a brew to the end:

Malt-- You'll need a way to crush the malt, unless you intend to buy pre-milled malt. A 2 roller mill is what is used for a smaller system (under 30 BBL). You want to size the mill so you can mill enough malt to dough in within 30-45 minutes. If your batches used 2000 lbs. of malt, you'd want to get a mill that could handle 3000-4000 lbs. of malt per hour, or get a grist case to receive and hold milled malt prior to mashing.

Water-- At a minimum, you'd have an activated carbon filter to remove chlorine, organic compounds, and some hardness from your water.

Mash tun / lauter tun-- The mash tun is used for mixing malt and hot water in order to aid in conversion of starch (in malt) to sugars through the use of naturally occurring enzymes contained in the malt. Brewers yeast mainly metabolizes simple sugar, so this is why the conversion of starch to sugar is critical in brewing. The lauter tun is a vessel for separating the solid malt particles from the liquid wort. Smaller systems have a combined mash tun / lauter tun, meaning the same vessel is used for starch conversion and for drawing the wort from the grain.

Boil kettle-- Once the wort is drawn off from the lauter tun, it is brought to a boil. Hops are added at different intervals in the boil for bitterness, aroma, and flavor. If you had a malt extract system, you would skip to this step. You'd add malt syrup or malt powder to filtered water, mix, bring to a boil, and add hops as usual. There are even no-boil extract systems where the extract is already hopped, but expect the beer to be pretty nasty. A typical boil is 60-90 minutes.

Whirlpool-- Some systems have a dedicated whirlpool, which is used for recirculating the hot wort in a centrifugal fashion, bringing the hop / protein solids to the middle of the vessel for easy separation of the liquid. Most systems just include a whirlpool port on the kettle to perform this function in one vessel. The advantage of having a separate vessel is when brewing multiple batches at a time, you can get the first batch out of the kettle and begin lautering / boiling your second batch. This would shave 1 to 2 hours from the total brew day if brewing two batches that day.

Heat Exchanger-- For sanitary and flavor purposes, you need to bring the wort down to 50-70 degrees fairly quickly once the boil is finished. A stainless steel plate heat exchanger is typically used. Cold water runs through one side, while the hot wort is pumped through the other side, resulting in a cooled wort once it makes its way through the heat exchanger. This is directly pumped into a fermenter.

Fermentation-- Typically cone shaped fermenters (cylindroconical) are used for fermentation, as their height takes up less of your valuable real estate, and the cone shape aids in yeast collection and trub dumping.  This is where the yeast is added, and the yeast converts most of the sugars in the wort into carbon dioxide and alcohol.  Fermenters should have jackets for running chilled glycol in order to control fermentation temperature.  Alternatively, you could have a temperature controlled room for regulating fermentation temperatures, but it'll be less precise and result in a higher electricity bill.

Cellar-- Once fermentation has ended, typically you'd have a brite beer tank for beer maturation, cooling, and carbonation addition. Beer is packaged (into kegs / bottles / cans) from this vessel.

Bottling / Kegging / Canning-- My numbers above didn't include this part of the brewing process. Kegging is usually the least expensive option, especially at the beginning when you don't need many kegs on hand. Bottling and canning lines can be very expensive. If you're looking to make a bottle conditioned beer, you can spend a lot less because your equipment doesn't have to deal with carbonated beer and reducing oxygen pickup is less of an issue. Of course, you could also use homebrew equipment for the bottling of carbonated beer, but don't expect to pay the bills by packaging that way (it's very slow).

I hope this info will help Nick and others!

Sunday, December 16, 2007

Infrastructure Details

Nicholas posted a comment in my last post that I thought was a great question, and possibly where this blog could be most valuable to future brewery owners. His question: "Where did you find out about all the requirement equipment, gas lines, water lines, etc. Can you point me to any books, articles, etc.?"

When you are looking for a place to lease/buy, make sure the utilities are there. Gas, 3 phase electric with sufficient amperage, decent water pipe size/pressure, and an easily accessible sewer line should be requirements. Avoid historical buildings because while they are neat and interesting, you may have additional hurdles and increased costs to deal with associated with historical preservation. Also, one of the more important things to watch out for is sufficient ceiling height (at least 14' high).

When you've found a space, your best resource is a good architect and a brewing consultant. Architects should be aware of all building code issues you'll encounter, and probably know what you need to operate a brewery. A brewing consultant can advise you to size your utilities correctly so your brewery will work efficiently. You'll save a lot of money if your landlord can give you "as built" plans of your space. Otherwise, the architect will have to survey the space and draw plans from scratch, which can be very expensive. Contractors / subcontractors should also be aware of code requirements.

For a frame of reference, I didn't hire an architect, and I didn't use a brewing consultant as much as I should have. I researched many of the things I needed myself by looking at other breweries and talking with other brewery owners about what they did and what they wished they did. My contractor and his subcontractors have been a huge help in my selection on materials. Typically, you don't want to rely on your contractor and the subs, as this will cause deviations from the plan and you'll run into "Change Orders", meaning additional costs and the possibility of the contractor taking advantage of you. Luckily my contractor is an honest guy so I haven't had any problems with my change orders yet. Anyway, I've learned a lot in the process of figuring out things myself, but as you'll see I've made mistakes that I'll have to live with.

Here's a list of the utilities you need, and the sizing considerations:

Water-- One of the most critical resources is a decent flow of water. A 1" line at 60-80 PSI would be great for a small brewery. Mine is 3/4" at 75 PSI, which is decent but the building only has 3/4" at the connection. It's pretty pricy to upgrade a water line to a larger size, so try to find a place with a large water line at the outset. My plumbers have run 3/4" copper pipe to the brewing areas for water connections. Also, something obvious but important-- the longer the run of pipe (of the same diameter), the less pressure you'll have. This applies to natural gas as well.

Gas-- Finding a building with a natural gas connection is essential, unless you want to start a brewery out in the middle of nowhere and all that's available is low pressure propane. The gas company is great about changing out the gas connection to your required size, so if the connection isn't sufficient, don't worry too much about it. Just make sure you're able to increase the gas line size on your end. I went with a 3" line, which is huge and probably overkill. For the equipment I currently have, I need around 2,000,000 BTU's. My gas line run is around 80 feet. A 3" line at 80 feet can deliver around 3,705,000 BTU's. If I ever want to add a larger kettle or more in-line water heaters, I have an extra 1,705,000 BTU's with my current gas line. The gas company is only giving me enough pressure at this point for 2,000,000 BTU's and will upgrade their end once I need more pressure.

Sewer-- It's important to check the depth of the sewer before leasing or buying a place, as this is something that is very expensive to change, if it's possible at all. I didn't check the depth of my sewer before signing a lease. Once I found out my sewer line was 17" below the ground, it was too late. I changed the configuration of where everything was to be placed to accommodate the short run to the sewer. There's a few ways to mitigate this problem if you come across it. The easiest is to upsize the sewer line you'll be installing for the floor drains. We went with a 4" line instead of a 3" line, which by code can have a lower slope to the main sewer. You can also pour concrete to raise the area to be drained, but this will cut into the ceiling height, which was a problem for me. The third option is using a sump pump for drainage. This can get pricy, and pumps aren't always reliable. If the pump fails, you'll be living in your own sewage until it gets fixed. Pneumatic pumps are the best option here as they are more reliable and if the power goes out, your air compressor tank will still have some air left in it. Also, if you're looking to start a brewery in a rural area, avoid septic systems at all costs. Waste water treatment for a small brewery is cost prohibitive, and without adequate waste treatment, you'll have to be very careful with what goes down the drain.

Concrete-- Most industrial / commercial buildings have 4-6" of concrete. The city will likely require a structural engineer to draw up plans for how these are going to be anchored, as well as calculations which support their recommendation. I found that my 15 BBL tanks could stay on the existing concrete slab and be anchored to it, but most of the brewhouse tanks as well as my 30 BBL tanks are too heavy and would have to be supported by separately poured footings. I decided to demo all of the concrete in the brewing area and pour a 12" slab. This allowed me to add floors sloped toward the drain, and the ability to add tanks in the future without pouring any new concrete. I also have 12" curbs that were poured monolithically (all as one piece), which have greater strength than curbs poured on top of an existing concrete slab that are simply anchored to the floor. I went with 3000 PSI concrete, which is fairly high strength and not that much more expensive than the standard 2500 PSI concrete.

Electricity-- The sizing all depends on the size of the operation, but my recommendation is at least 200 amps of 3 phase electricity. I leased the space thinking I had 200 amps of 3 phase, but it turned out I had 175 amps of single phase electricity. I had to add the 200 amp / 3 phase panel, and luckily I'll be able to keep the existing single phase electricity as well. I wish I had 400 amps of 3 phase, so I'd recommend that to you too. My glycol chiller requires 60 amps of 3 phase power by itself. When I'm in the middle of brewing and many other devices are also running, I'll be close to pulling all 200 amps at once.

Roof Weight Capacity or Side Yard-- You'll need a place to put your glycol chiller, and most of them emit a lot of heat (unless they are liquid cooled), so outside is the best place for them. Mine is going on the roof, and by the size of the platform my contractor is putting on the roof (3' x 18') I'm learning the roof can't handle too much weight. Make sure your city / landlord allows large machinery on the roof. If you're in an industrial area, there's a good chance there won't be a problem. If I had a locked side yard, I would have put the glycol chiller there, along with a malt silo and whatever I don't need to store indoors.

Venting-- I've had to make quite a few roof penetrations to vent all of the equipment I'm putting in. I have three water heaters, all with their own vent. My kettle needs 2 vents-- one for steam, one for combustion exhaust. If you choose a building with multiple stories, you will either have a long draw vent or a vent from the side of the building (both of which will probably require exhaust fans). Keep in mind your neighbors might be taking in air from the same area you are venting to, so plan carefully if you aren't venting straight to the roof. I'm in a single story building, so my vents are relatively short and don't need fans.

HVAC-- This is a big issue I haven't addressed yet. The Health Department has required that I keep the doors closed at all times, so when I'm brewing on a 100 degree day, I can't open the place up to get a breeze through. I don't have enough power (or money) to add a huge air conditioning unit, so we'll probably be brewing early in the morning to avoid the hottest times of the day. I'll likely add intake fans to bring in filtered outside air in a few months as summer approaches, but I'm not giving this too much attention until it becomes a problem. I'm thinking of inventing glycol cooled clothing, but I have too much on my plate right now to get into that. If someone wants to run with that idea, feel free to do so! I'll be your first customer! Maybe I'll just buy these: http://www.mscooling.com/home?gclid=CN2C4_XWrZACFRdPagodKzaI7Q

This is all I can think of for the moment. If anyone wants to read it, I could prepare something similar for how I've chosen my brewing equipment.

Saturday, December 15, 2007

Just a Few More Weeks...

Sorry for not posting lately, but seeing that Rachel and Tyler have been doing a great job with their posts in my absence, why change a good thing? Well, because Rachel might not be posting for a few weeks. On Wednesday, she underwent emergency surgery due to an infected cyst on her tailbone that flared up in the past week. She is doing much better now, but it'll take some time before everything is back to normal. Her Mom and Barley have been taking very good care of her, and I'm trying to do my part and make sure everything at The Bruery is still getting accomplished.

Construction has been coming along nicely, and we're thinking completion should be in the next few weeks. The gas line, water lines, water heaters, etc. have been installed, power will finally be turned on this Tuesday, everything has been painted, and most of the equipment has been set in place. The few key things that remain are to have the glycol chiller placed on the roof, the glycol plumbing installed, Gas Company installation of a new meter and gas manifold, sealing the floors, some electrical work, welding, and the kettle flame system. Most of these items will be completed before New Years. I still need to order malt and yeast for the first few batches as well. Mid-January for the first batch seems like my best guess at this point.

I'm very happy I hired Tyler when I did-- he's been a huge asset in getting things to where they need to be so we can start brewing. My guess is it would have taken an extra month if I was doing all of this by myself.

On Monday I'll post some pictures of the progress.

Thursday, November 29, 2007

Framing Complete And Lots of Other Stuff

Yet another milestone (there will be lots of those coming in the next few weeks)-- the vestibule has been framed, the city inspected it a few hours ago, and dry wall is going in today.

The plumbers are currently installing the copper piping for my sink area, and this area will be drywalled at the same time as the vestibule.

Tomorrow insulation will be replaced for half of the warehouse. They'll have to come out twice because the other side of the warehouse is packed with brewing equipment and bottles, so once the equipment is put into its final spot, I'll move all of the bottles outside and they will finish the insulation for the rest of the space.

This Monday and perhaps Tuesday the Stonhard urethane (UT) flooring is going in. Once it is in, I'll be able to start putting tanks where they belong and start connecting everything.

Another exciting event on Monday-- Tyler begins working for The Bruery. He will be much needed in setting up the brewing equipment and getting miscellaneous tasks done before Christmas so we can get our first batch brewed on January 2nd. There's a lot of things to do, and one minor omission could hold up the first batches by a few weeks, so Tyler will be of great help in getting things done. He appears to be excited about doing whatever it takes to get the doors open, so I know he will be a pleasure to work with.

Speaking of brewing our first batch on January 2nd, that leaves only 34 days to finish everything up. In reality, I only have 22 days to get everything done and pass inspections as after Dec. 21st, nothing will get done. The City is closed from Dec. 22nd until January 2nd, and I imagine the OC health department has a similar schedule. Did I say January 2nd we'd brew the first batch?

Wish me luck!

Tuesday, November 20, 2007

Concrete Going In

Fifty to sixty cubic yards of concrete are going in as I write this and it's exciting as hell. The concrete and sewer are the most time intensive parts of the construction process, so things should be progressing nicely after this. Brewing equipment installation is scheduled for December 5th, the day after the Stonhard flooring is put in. Back to take more pictures and watch more concrete get poured.

Friday, November 16, 2007

Not Just a One Man Show Anymore

Over the past few months, a lot of things have happened while setting up this brewery, but two in particular have greatly changed my approach of running the business. The first is I've realized I can't do everything myself. I can't be the only person making the beer, maintaining the brewery, selling the beer, delivering the beer, promoting the beer, and so on if The Bruery is going to be successful. The second thing is I've had the opportunity to get to know a talented brewer at a time when he's ready for the next step in his brewing career. A few months ago, Tyler King told me he wanted to work at The Bruery from the very beginning, and he'd do it for free (don't worry EEOC, he'll be getting paid). Tyler wants to have the experience of being at a brewery from the ground up, and I need his help and expertise, so it was a match.

Tyler has been brewing with BJ's for around 5 years and is particularly skilled in yeast culturing and quality assurance / lab analysis. He is a great homebrewer as well, and is interested in brewing with wild yeast and souring organisms which will be right up our alley. If you stop by the brewery relatively soon, you can try his excellent Flemish Red on tap. He will be graduating from Cal State Fullerton in the Spring, and his last academic hurdle will be completing an internship in Marketing/Advertising at The Bruery. He'll be in charge of marketing our summer seasonal. Tyler and I will share in the brewing responsibilities, and at the beginning when our brewing schedule isn't too demanding, he will be working on sales as well.

Cheers to Tyler-- I'm looking forward to working with you.

Monday, November 5, 2007

Construction Has Begun

Ahhhh, finally!  On Friday the concrete floor was cut in the perimeter of where it will be removed, and today the jackhammers come out and the floor (plus a foot of dirt) will be taken out.  There's a pretty decently sized tractor parked in front of The Bruery, so it shouldn't take too long.  After that, the rebar will be added to reinforce the concrete, the plumbing will be placed, and the floor will be poured back with a 1 foot high x 6 inch wide curb and sloped.  All of the plumbing and rebar will be put in this week, and it looks like pouring back the concrete will be happening next week.

I recently found out that the concrete will need to cure for at least 14 days (probably more like 21 days) until the Stonhard Polyurethane mortar flooring system can go in.  I was hoping to start placing the tanks a week or two after the concrete went in, but that's not the case.

Construction and equipment setup should be finished just before Christmas time, so I'm hoping to get the first batches in the fermenter before the new year.  If that happens, it'll be late January / early February before we open the doors.

I'll make sure to post timely pictures of the process.

Monday, October 29, 2007

Construction About to Start

Good things have been happening, but I was hoping to have a picture of a pile of concrete to show you by now. The good news is I picked a new contractor after receiving five bids, and I know he's going to do an outstanding job. The plumber is coming by today to lay out the area, and I'm hoping we can get the concrete work started this week.

This is probably a bit on the dry side, and in fact I get a headache when writing about it. Read it if you care, otherwise I'll try to come up with something a bit more entertaining for the next post.

The concrete work entails cutting out around 1100 square feet of concrete in the brewing area and in the sewer line area, removing a foot of soil, placing a 35 foot trench drain, and pouring a foot of sloped, reinforced concrete, along with a 1 foot curb which will act as a containment area (a city requirement). The area where the sewer line is going will be filled in, and then I'll wait 7 to 10 days for the concrete to cure before the urethane flooring can go in. Once the urethane goes in, I can put my tanks where they need to go, and start setting up equipment. The plumber can then install the water and gas to the brewing area (and the four sinks), my welder can get to work on piping together the brewhouse, the electrician can hook up my equipment, and the burner technician can piece together the combustion system for my boil kettle.

While all of this is going on, drywall is going up to form a vestibule around one of my cargo loading doors (a health department requirement), the office will have wood flooring installed, a glycol chiller / structural platform will be built on the roof, every wall will be painted, and all concrete will be sealed. A few miscellaneous items like hooking up a few augers, getting city and health department inspections, and dealing with my own sanity will be involved as well.

Exciting stuff, and I pray to God it all gets done quickly. You and I have been waiting far too long!

Wednesday, October 3, 2007

More Guessing About Launch Dates

Alright already, I should probably not throw out any more opening dates. I don't know what it is with brewery startups-- we have a compulsion to announce dates that in our limited experience seem plausible. Maybe it's a case that if we announce it and believe it, it will actually come true? I'll try to explain what happened, and hopefully you'll understand why you aren't drinking a Saison Rue right now.

On May 22nd, when I initially leased 715 Dunn, I proclaimed The Bruery would start brewing in August and start selling in September. Early on I had an architect that was going to put together the plans, but then shortly after I decided I could draw up the plans on my own and save $5,000 - $10,000 in the process. Strike one. Architects know what they are doing, and I don't. I think I would have saved two months if the architect drew up the plans. What does two months of rent and lost opportunity cost? Probably more than an architect.

On June 27th, I thought I'd be ready to start construction. My plans were put together (or at least I thought they were), and I was ready to get a bid from a contractor I already picked out. Getting just one bid? Strike two.

After I got the bid (or more accurately an estimate because the contractor had no idea how to price out my less than detailed plans), I figured I could get my plans approved by the city over the counter and start construction. I learned the city won't accept the plans until they are approved by the Health Department. Better get my plans into the Health Department, no big deal. Health Department approval is only a formality, as they don't care about breweries-- right? Wrong! Health Department approval takes about 2 months due to my need to negotiate to lessen what they required of me. Strike three (thankfully, this isn't baseball). I learned that you don't negotiate with the health department, at least if you want to get your plans approved. They did make some concessions which will save a bit of money and time, but overall I would be in a better position had I went with the flow.

I finally get my plans approved by the city on September 20th (which takes two weeks, and is not done over the counter), and I'm finally ready to start construction. I eagerly call my contractor, leave a message. Call an hour later, leave another message. Repeat for two days. Finally get a hold of him, and he says how busy he is, and how he'll call me right back. That was two weeks ago, and still no word from him. I've learned enough by now that I probably wouldn't be getting a call back from him, so then I called several contractors for bids.

For the last two weeks, I've been dealing with general contractors and subcontractors in their bidding process. Today, I'm waiting on several bids. I should have all of them by the end of this week, or more accurately, the bids I'll be considering will be in by Friday.

So what needs to happen before The Bruery can open? Construction needs to start. If I pick a general contractor this week, there's a chance they could start next week, but more likely it'll be the following week. Construction will take a minimum of four weeks. The Health Department needs to inspect, and will probably have some changes they'd like to see. Add two weeks. The City needs to inspect, and perhaps there's another change that needs to happen. Add another week. During this time after construction, equipment is installed. Most of the equipment installation will be fairly straight forward, except for the kettle burner system. I can't do much with the direct fire burner system until the kettle is in its proper place, so I'm not sure how long that will take. Let's just say my best guess at this time is it'll be another 8-10 weeks before I can brew the first batch, which would bring me into the first week of December. If that comes true, I think a New Year's Day grand opening party is called for. 2008 is my year!

I've learned a lot going through this, and gained some grey hair and a few inches in the waistline as a result. This is a blog about my experience opening a brewery, so I should state what I would have done differently if I had to go through this experience again. If I could go back in time to May 22nd, I would have done the following:

- Hired an electrician to confirm I had three phase power before I signed the lease.
- Hired a plumber to confirm the sewer depth before I signed the lease.
- Hired an architect to draw up the plans
- Received multiple bids from contractors
- Submitted my plans to the Health Department ASAP even if the plans were not as complete as they should be
- Make the changes the Health Department required without debate
- Overestimate how long things actually take
- Remember that each day I am not open costs $134 in rent ($5.58 an hour!), and much more in lost opportunity. Hiring out is often the less expensive option when you don't have the experience or time to complete that task
- Give a moment to celebrate each achievement, and then move on to the next item on the list
- Don't blame myself or others when it isn't productive

This list could go on, and I'll probably add to it when I learn of other things I should have done and should be doing. I hope this is useful to those of you who share the same dream of opening and running a brewery. It's therapeutic for me to write this and get a better sense for myself of why it is October 3rd and I haven't started construction yet. As for other advice I need to give myself, do as much as you can every day, and remember that everything has a lead time, no matter how small the task seems to be. When the opening of a business is dependent on many things outside of your control, and those with control don't have an incentive to be expedient, don't estimate on how long they will take, and more importantly don't take guesses on when the business will be open. Don't be hard on yourself when your guesses don't come true-- you're doing the best you can.

Thanks for reading this blog and for supporting my dream of running a brewery.

Thursday, September 27, 2007

Writing Mission Statements

Mission and vision statements are an important part of any business, especially in the first few years of a new business. What is the purpose of this business? Who does the business serve? What expectations are there for the future of this business? If there aren't clear answers to these questions, it is unclear what steps to take to produce a successful result.

I'm sitting here at The Bruery in a dim office, looking at a few hundred ants on a nearby table. I made the mistake of leaving a wrapper on the table yesterday, and a civilization is now able to eat because of me. I kill a few just for the fun of it (where did I put my lighter?), and I'm frustrated. Don't take it out on ants, Pat. On the desk behind me, there are a dozen sheets of notepaper, with scribbles and barely legible writing about goals and purposes. I'm trying to come up with a one sentence mission statement that says it all. I don't want to include any semi-colons or too many commas. I want it to be short, sweet, and say everything that I want the brewery to be with some specificity. Impossible? I think so.

It's an odd time to be coming up with this. The Bruery consists of me and a bunch of equipment that is non-functional. There are lots of ideas, of course. I'm trying to get construction started so I can get on with my life and start making beer. When I'm trying to come up with a mission statement, I'm thinking of a bustling brewery with many bright workers, thousands of loyal customers, and a clear sense of what The Bruery is. At this moment, nothing is clear, not even my eyeglasses. I can't remember the last time I cleaned those.

My Dad and I meet on a weekly basis. He is my advisor and business coach, and has a great deal of knowledge on how to run a company and come up with goals and strategies. He gave me the assignment of coming up with a single sentence that describes why I'm doing what I'm doing. There are so many reasons-- I hate the law (not the law itself, just advising others on it), I love making beer, drinking beer, and being in the company of people who share a similar interest in beer. I want to be in a craft-related business-- making something for the enjoyment of others. Sure, I want to make money too, but that's not why I chose to be in the beer business. I want to share beer with others, and I want The Bruery to have an impact on the beer industry as a whole. I'd like to be the cause for many to experience a new side of beer-- a paradigm shift that makes someone realize that beer is so much more complex, interesting, and enjoyable than what they had previously believed.

The best thing I can come up with is pretty vague, but I think it makes more sense when I explain the different parts:

"The mission of The Bruery is to enjoy crafting unique beer for the enjoyment of our supporters."

To address each part of the mission statement-- "To enjoy crafting...": I want to get out of bed every morning and be excited to run The Bruery. Whether it's making beer, selling beer, or managing the business, I'm doing it because I enjoy it. If I don't enjoy it, then I'll need to find out why and correct it. I think making money is addressed in this section of the vision statement, as I probably won't be enjoying what I'm doing unless I'm able to make a living doing it. Likewise, I want those who work at The Bruery to get the same enjoyment out of being here as well. If they aren't enjoying it, I want to know, especially if it increases the enjoyment for everyone else.

"...unique beer...": Our beers should stand out from others on the shelf and give us a sense of pride that we're doing things our own way.

"... for the enjoyment of our supporters.": The word "enjoyment" is quite vague, but we want people to like our beer. We want people to have the beer in an atmosphere of enjoyment, and I think most craft beers are had with this in mind. Whether the person having the beer is experiencing this beer for the first time and is being exposed to a world of new flavors, or this beer is an old standby, we want that person to find value in our beer and not be disappointed by it. Thus, we'll have very high standards of quality. If I don't like it, I won't expect anyone else to either. Our beer may not be compatible with everyone's tastes, but it will be a priority to make sure those who enjoy complexity in their beer are enjoying our beer. Developing a relationship with those who enjoy our beer, or our "supporters", is important to me. I think having a connection to the customer is one of the things that will make it enjoyable for myself and for future workers of The Bruery.

What do you think of this as a mission statement? What am I missing?

Hop and Malt Prices

If you check out other beer blogs, you've probably heard that hops are in short supply in this 2007 harvest, and prices are going through the roof. I'm trying to contract out some hops for this next year, and most places don't believe they have enough supply to enter into those contracts this late in the game. Even if they could sell me the hops I want, prices are about double of 2006 harvest prices. So what the hell am I going to do?

I'm in the process of securing all the hops I'll need for the year by getting my hands on what's left over from the 2006 harvest. I've been able to get Czech Saaz, Styrian Goldings, US Sterling, German Magnum, US Warrior, and US Summit. I have 440 lbs. of hops in inventory, and I'll be buying more in an attempt to hold me over until the 2008 harvest. All of these are vaccum sealed and have been cold stored (and are now stored at 10 below), so they should be very fresh. Most of my hop usage is for bittering, so I'm somewhat fortunate to be focusing on Belgian-style beers, seeing that most are in the 15 - 35 IBU range and tend not to have too much in the way of aroma hops. I'm a big fan of IPA's and Double IPA's, so I hope this shortage and price hike doesn't affect those styles too much.

As for malt prices, they are expected to climb 50 - 100%. There isn't much I can do about that, but I haven't heard of any talk of not being able to secure malt without a contract. I'll be looking into this more. It doesn't help that I don't have a silo-- bulk storage of grain is out of the question for me right now.

Thursday, September 20, 2007

Plans Approved by City

Finally, we're ready to start construction! Plans were approved this morning by the City of Placentia, and my general contractor just needs to pull the permit, and I need to pay a hefty fee. Seems easy enough, right? The only thing holding me back is that my contractor isn't returning my phone calls. The City is closed tomorrow, so the permit will have to be pulled on Monday.

Regardless, I'm trying to reflect on the accomplishment that my plans were approved, and things can finally move along. I think celebrating all of the small achievements along the way is important in keeping sane, and as a reminder about what I'm trying to do. I'm not in the business of building breweries; I'm in the business of brewing beer. I now know how to start a brewery, and I hope I'll remember how to brew when it comes time!

If construction starts next week, I'm aiming to start brewing in late October / early November. If that's correct, then I'd be on track to sell bottles / kegs in early December. I haven't been right on guessing when things would get done previously, so I probably shouldn't be putting dates out there, but I will anyway. I'm really looking forward to brewing a winter seasonal, so I pray this timeline pans out.